WORKING HISTORY

  • Execution works of the electrical network system project for medium voltage (11 kv) and low voltage (0.4 kv) for five villages in Erbil governorate with a length of (45 km) with the installation of transformers and their required bases.

  • Execution works of medium voltage network project (11 – 33KVA) with all the modifications required to transferring the electrical power to the Rzgary intersection project in eight stages at a total cost ($2,000,000) .

  • Execution works of the medium voltage electrical network system project (11kv) for the village Goma Shin, with a length of (12km), with the installation of transformers and their required bases.

  • Execution works of the medium voltage electrical network system project (11kv) and low voltage for a residential complex (Aynda 1 -2) , with the installation of transformers and their required bases and internal connections to the project.

  • Execution works of the medium voltage electrical network system project (11kv) and low voltage for a (hewlery nwe 1 -2),with the installation of transformers and their required base sand internal connections to the project.

  • Worked in smart meter project in 2019, in Erbil, we were the first company that installed the first smart meter box in the south industry area.

  • Execution works for petrol company in Qayara, installation of71 poles with three transformers.

  • Transferring six mobile substations in 2021, in twelve different areas within the borders of Erbil Governorate.
    – Transferring nishtiman mobile station to dara shakran. Transferring koya mobile station to makhmur .
    – Transferring karezan mobile station to timar industrial area.. Transferring hawkery mobile station to taq taq .
    – Transferring nwsaran mobile station to makhmwr-bazarga .. Transferring shaqlawa mobile station to soran .